Work completed/in progress:
- Forms and reinforcing steel are being installed for the first wall pour.
- Base slab has been backfilled.
Anticipated work activities for the coming week:
- Installation of steel and construction of bulkheads will continue, with a pour tentatively scheduled as early as Friday.