Construction has finally started on the Courtland Township pump stations. K&R is starting at Pump Station 8 and plans to start at Pump Station 5 in mid-November. Both stations should be complete by the end of the year.

Pump Station 8

Work Completed:

  • Bypass connection and valves installed, bypass pumping started
  • Old equipment demolished and removed, wet well cleaned, electrical service disconnected
  • New piping and valves mostly installed

Upcoming Work:

  • Complete installation and testing of new piping
  • Cut existing structures and install new lids
  • Install new pumps

Traffic Control:

  • Bypass pumps are installed in the middle of Hessler and Orlin with cones and barricades
  • Traffic lanes remain open and driveable through intersection