Work completed/in progress:
  • Completed installation of trenchless casing beneath Railroad spur and finishing trenchless casing adjacent to the Consumers substation.
  • Stripping topsoil and installing soil erosion and sedimentation control measures.
  • Taking delivery of pipe materials.
  • Locating existing utilities.
Anticipated work activities for the coming week:
  • Pipe materials continue arriving.
  • Begin fusing pipe and perform destructive sampling.
  • Begin pipe trenching and installation.