Work completed/in progress:
  • Excavation for the new lift station structure is complete and mud mat is poured.
  • Steel for the base slab has been delivered to the site.
Anticipated work activities for the coming week:
  • Grand River Construction will begin tying steel reinforcing for the base slab (anticipated to take 1-2 weeks).