Van Buren – Butternut to US-31
- Van Buren from Butternut to US-31 is closed.
- Road building between 140th and 136th continues. Next week, the first layer of asphalt will be placed from 140th through 136th Ave.
- Restoration between 152nd and 144th continues.
- Work on miscellaneous transmission main items continued.
- A repair to the transmission main near 140th Avenue was completed.
- Work inside the pipe continues.
164th – New Holland to Van Buren
- 164th Ave is closed between New Holland and Van Buren.
- Unsuitable soils were removed from the work area in advance of transmission main installation.
- Transmission main installation will begin first thing next week on the south end of 164th Avenue.
Van Buren – US-31 to 96th Avenue
- Van Buren from US-31 to 120th Ave is closed.
- The Van Buren/120th Avenue intersection is scheduled to close late next week for approximately two weeks.
- The tunneling operation beneath US-31 has been suspended for the time being.
- Work was completed on valve vault piping and adjacent appurtenances near 128th Avenue.
- Transmission main installation will begin first thing next week just west of 120th Avenue, progressing east.
New Holland – 104th to 96th & Easement
- Van Buren Street between 104th and 96th Avenue is closed.
- Work continued on pipe appurtenances adjacent to Van Buren Street.
- Next week, the interior of the pipe will be prepared for final acceptance testing. Acceptance testing is scheduled for the weeks of September 21 and 28.
Drinking Water Plant – Surge Suppression System
- Basement plumbing passed air testing.
- Basement slab rebar installation is underway.