Progress Report:
K&R continues to make progress on laying 21-inch gravity sewer along 120th Ave towards James Street. A second crew began laying water main in the James Street and 120th Ave intersection earlier this week. The new water main is expected to be installed, tested, and connected to the existing system prior to laying gravity sewer in the intersection.
The James Street and 120th Ave intersection will remain closed the duration of the construction. Detour routes and local traffic access will remain in effect.