Work completed/in progress:
- Tree clearing and brushing along 64th Avenue and the Coopersville & Marne Railway corridor has been completed.
- Contractor is installing trenchless casing beneath Railroad spur on Continental Dairy’s property. (see attached photo of bore pit)
- Consumers relocated guy wire near Continental substation.
Anticipated work activities for the coming week:
- Continue installation of trenchless casings on northern edge of Continental Dairy’s property.
- Strip topsoil and install soil erosion and sedimentation control measures.
- Locate existing utilities.
- Pipe materials start arriving.
- Begin fusing pipe and perform destructive sampling.