Van Buren – Butternut to US-31
Van Buren from Butternut to US-31 is closed.
- Road building between 140th and 136th continues.
- Restoration between 152nd and 144th began.
- Work on miscellaneous transmission main items continued.
- Next week there will be an excavation near 140th Avenue to make a repair to the transmission main.
- Work inside the pipe continues.
164th – New Holland to Van Buren
164th Ave is closed between New Holland and Van Buren.
- A haul road was constructed this week to aid in transmission main installation.
- Transmission main installation will begin later next week.
Van Buren – US-31 to 96th Avenue
Van Buren from US-31 to 120th Ave is closed.
- The tunneling operation beneath US-31 has been suspended for the time being.
- Work continued on valve vault piping and work on adjacent appurtenances near 128th Avenue. This work is nearly complete.
- Next week, the pipe crew will begin pipe installation near 120th Avenue.
New Holland – 104th to 96th & Easement
Van Buren Street between 104th and 96th Avenue is closed.
- Work continued on pipe appurtenances adjacent to Van Buren Street.
- Next week, work will continue in Van Buren Street.
- The interior of the pipe is being prepared for final acceptance testing.
Drinking Water Plant – Surge Suppression System
- The sump has been constructed.
- Basement plumbing has been installed and encased in concrete.
- A mud mat was placed.
- Next week, work on the basement slab will continue.