Work completed/in progress:
- Control panel and air handling unit delivered.
- Electrical equipment and lighting installation started.
- Additional 24″ force main laid.
Anticipated work activities for the coming week:
- Install drain line from building.
- Form and pour sidewalk footings and foundation walls.
- Finish duct work.