Progress Report:

The contractor continues to install sanitary sewer towards the south to tie into the sanitary sewer that was constructed last year north of Port Sheldon Street.

Upcoming Work:

The contractor plans to begin the bore and jack operation for water main this week under Rush Creek for the water main and will be mobilizing today. The bore and jack operation will require a full, hard closure of 48th Avenue at Rush Creek.

Note:

We ask the public to respect the workers and the closed road. Police will continue to be present to safe working conditions and to ensure the road is only being used sparingly by those who live or work on this road and not by though traffic.