Progress Report:
The contractor has begun excavation for the bore and jack operation under Rush Creek. Wet weather caused delays with excavating the pits for the bore and jack equipment. The extent of operations for the bore and jack requires a full, hard closure of 48th Ave.
The contractor continues to construct the sanitary sewer to the south to the tie in point.
Upcoming Work:
The contractor is continuing to dig bore pits to be able to install the casing under Rush Creek. They plan to have the bore and jack of the casing finished by the end of the week. The contractor hopes to have the sanitary sewer finished by the end of this week or early next week. After that, the contractor will continue with water main construction.
Note:
We ask the public to respect the workers and the closed road. Police will continue to be present to safe working conditions and to ensure the road is only being used sparingly by those who live or work on this road and not by though traffic.