Construction on State Street and Main Street is moving quickly, with the completion of utility mains installation on Main Street East of State Street.
North bound and south bound traffic on State Street is being maintained until work is completed on Main Street East of State Street. Road closure will be in place from the centerline of State Street east to the project limits. Main Street traffic east of State Street must continue to follow the posted detour.
Work Completed Last Week:
- Water main installation on Main Street, east of State Street.
- Water main tested, cleaned, and sampled.
- Storm sewer installed on Main Street, east of State Street.
Anticipated Work This Week:
- Water main will be connected to the existing system at the east limit of the project on Monday April 20th.
- Water service connections from the new main to the businesses on Main Street.
- Removal of sidewalk on Main Street, east of State Street.
- Continue storm sewer installation on State Street east of the road centerline.