Progress Report:
The contractor has milled 48th Ave south of Rush Creek and has milled the east side of the road up to Tyler St and is working to maintain adequate access for residents and businesses in the construction zone.
Upcoming Work:
The contractor will begin installing sanitary sewer this week south of Rush Creek and will work their way south to tie into the sewer that was installed last year just north of Port Sheldon St. In addition, the contractor will begin a bore and jack operation under Rush Creek ahead of the water main installation. The bore and jack operation will take place next week beginning on Monday. This will result in a full, hard closure of 48th Ave at Rush Creek.
Note:
We ask the public to respect the workers and the closed road. Police will continue to be present to safe working conditions and to ensure the road is only being used sparingly by those who live or work on this road and not by though traffic.