Work Completed this past week (March 31 – April 4)
- Aerial crossing completed and sanitary sewer pipe installed across McCoy Creek to 3rd Street.
- Existing 18” sanitary sewer connected to prop. 24” sewer at SNE1.
- CCTV of 24” sanitary sewer from SNE1 to Prop. Flume completed.
- Installed (4) Inserta-Valves for Main St/Dewey water main shut off. No water shut offs currently planned.
- Water main install complete on 3rd Street. Remaining water main on Main Street (Dewey to Front) planned for Sat (4/5).
- Sanitary sewer bypass at WWTP complete, old flume no longer in operation (except for septic dumping). All sewer going through new flume as of Thursday (4/3) end of day.
- 3rd Street closed at aerial crossing on Thursday (4/3). Access to Red Bud Fitness and City hall to use 3rd Street/Red Bud.
- Construction Photos can be viewed with links on the construction website (left hand side).
Work planned for this week (April 7 – 11)
- Continue sanitary sewer install on 3rd Street.
- Contractor to relocate/calibrate flow meter at new flume.
- Begin testing installed water main.
- Connect prop. Water main to ex. Water main (East end of Dewey).
- Water services to begin week of 4/14.