Work completed/in progress:
- Preparing site for force main installation including butt-fusion of pipe, topsoil stripping, and dewatering installation.
- Force main installation has been delayed due to a delay in arrival of force main materials.
Anticipated work activities for the coming week:
- Begin preparing Ensley Rd extended (south of Apple Avenue) for force main installation.
- Force main materials expected to arrive this week and force main installation to start the week of December 16.