**Heights Ravenna Rd between Moorland Rd and Ravenna Rd is closed. Heights Ravenna Rd will be reopened to traffic by Thursday, July 17***

 

Work completed/in progress:

  • Installed maintenance structures along force main.
  • Complete Swanson Pickle driveway restoration.
  • Began restoration efforts.

Anticipated work activities for the coming week:

  • Complete installation of maintenance structures.
  • Pressure test installed force main.
  • Continue restoration.