Work Completed:
- Force main interconnect south of I-96 is complete.
- Deer Creek crossing has been completed and the creek restored.
- Installation of the sanitary sewer and force main north of I-96 has been completed.
- Biosolids removal in Pond 2 is complete, with the Polishing Pond expected to be completed today
- Pressure test the HDPE force main and sanitary sewer under and north of I-96.
- Perform restoration and clean up north of I-96.
- Continue installation of sanitary sewer along the south side of I-96.