Progress Report
- Broadway: Restoration work is ongoing with final touches to concrete and structure adjustments before the final course of asphalt is placed soon. THE ROAD IS STILL CLOSED TO ALL TRAFFIC.
- Delano Avenue: Underground utility work is essentially complete, and road restoration is waiting for a couple of utility poles to be relocated next week. Road restoration should be complete in the next few weeks.
- Sanford Street: Underground utilities are completed and the road is being rebuilt now. Gravel road base is being placed now.
- Oakwood Avenue: Water main connections are taking place along Oakwood between Glade and Mona. Many connections are complete.
- Amsterdam Avenue: Water main is installed and will be tested before connection to the City system next week.
- Getty Tank: Sandblasting and painting of the tank continues. Roughly 40% of the work is complete now.
- Lead Service Lines continue to be replaced throughout the City
The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.
The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street
The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue
Upcoming Work Planned for Next Few Weeks:
- Broadway: Manhole and valve structures will be raised in the new asphalt. Final restoration and paving will be done in the next 2 weeks.
- Water service replacements are happening all over the City as part of the Lead Service Line Replacement program. This work will dramatically increase next week through August.
- Delano: Road and lawn restoration will take place between Reynolds and Getty after the paving is completed in the next 2 weeks.
- Sanford: Gravel road base will continue to be placed and concrete curb and gutter will be installed next week along with new concrete sidewalk and driveway ramps. Asphalt will be done the first week of August.
- Oakwood: Water main connections will continue in Lemuel and Waalkes. After they are completed, road restoration will take place at all sites.
- Amsterdam: Water main will be tested next week before connection to the City system. It will be tied in and then water services will be replaced. New storm drains will be installed in intersections.
- Getty Tank: Blasting and painting will continue and the driveway to the tank from the cemetery will be completed