  • Van Buren Street from Butternut to 136th Avenue is closed.
  • Next week, Van Buren Street from 136th Avenue to US-31 will be closed and preparations for pipe laying will begin including road removal, installation of dewatering, and pipe staging.
  • Road building between 160th and 152nd continues. Paving for this length of road has been rescheduled for the week of July 13.
  • Pipe laying between 152nd and 144th Avenue has progressed to Pond Drive and will continue eastward next week.
  • Pipe laying between 144th and 136th Avenue has progressed halfway between 140th and 136th Avenue and will continue eastward next week.
  • Work inside the pipe continues.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • Pipe laying is expected to resume near the end of July.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Work continued on various pipe appurtenances within New Holland Street.
  • Valve vault and valve installation have been completed and the remaining pipe will be installed next week.
  • Work in New Holland Street will continue next week in preparation for paving.
Contact a Location
Learn About Us
View Our Services
Facebook-f Linkedin Youtube Instagram

© 2026 Prein&Newhof, All Rights Reserved

  • Plan Room
  • Lab Results
  • Construction Updates
  • Survey Request