Work Completed this past week (May 27-31)
- Continued sanitary and storm sewer install on 3rd Street at City Hall.
- Installed vibration monitoring equipment on Front Street.
- Dewatering Treatment unit power washed prior to removal.
- Construction began on Front Street. Closed to traffic from Oak Street to East of Red Bud.
- Oak Street intersection closed to traffic on Friday (5/30) to Wed (6/4) for water valve install.
- Street lights removed. Temp street lighting installed.
- Front Street Closed (Eastbound lane only) between Liberty and Rynearson sfor Retaining Wall repair (not part of Infrastructure project).
Work planned for this week (June 2-7)
- Continue storm sewer install on 3rd Street at City Hall.
- Water main tie ins on Red Bud, 3rd Street, Dewey Street planned for Tuesday (6/3) /Wednesday (6/4).
- Begin sanitary sewer install on Red Bud, South of 3rd Street. Red Bud South of River will not be accessible to thru traffic.
- Install insert valves at Oak Street/Front Street intersection Tuesday (6/3).
- Begin water main install at Red Bud/Front Street.