All underground work on the project is now complete! Work is now focused on rebuilding the roadway and sidewalk. The next couple weeks will be very busy with concrete being placed throughout the project and road grading being completed at the same time. Exercise caution if entering the project site!
Work Completed Last Week
- Final water main connections were completed.
- Sidewalk removal and grading for new sidewalk throughout the project site.
- Road gravel was placed from Terrace to Wood.
Anticipated Work This Week
- Concrete placement for Curb and Gutter, Sidewalk, and Drive Approaches.
- Grading of road gravel for new curb and for final paving.