Work Completed:
- Pumps, valves, piping, and electrical demolished
- Yard piping installed and tested
- Process piping, valves, conduit, interior equipment pads, and control panel installation started
- Generator pad frost walls poured
Upcoming Work:
- Generator pad pour
- Pump base pours
- Electrical conduit and MCC installation
- Wet well cores and suction pipe installation