Work completed:
- Trenchless crossing of the 8″ HDPE sanitary sewer beneath I-96 completed via horizontal directional drill.
- Force main interconnect and 8-inch PVC sanitary sewer installation started
- Biosolids removal at the Coopersville WWTP is underway
Upcoming work:
- Complete force main interconnect south of I-96 and pressure test
- Complete installation of the 8-inch PVC sanitary sewer
- Continue Biosolids removal within the Emergency Storage Ponds
- Force main and sanitary sewer will be installed across Deer Creek north of I-96 within the next month, weather permitting