Work completed:

  • Trenchless crossing of the 8″ HDPE sanitary sewer beneath I-96 completed via horizontal directional drill.
  • Force main interconnect and 8-inch PVC sanitary sewer installation started
  • Biosolids removal at the Coopersville WWTP is underway

Upcoming work:

  • Complete force main interconnect south of I-96 and pressure test
  • Complete installation of the 8-inch PVC sanitary sewer
  • Continue Biosolids removal within the Emergency Storage Ponds
  • Force main and sanitary sewer will be installed across Deer Creek north of I-96 within the next month, weather permitting