Work completed/in progress:

  • Dry well stair installation nearly completed.
  • Metal roof installation started.
  • Continue preparation for wet well lining.

Anticipated work activities for the coming week:

  • Continue roof construction and preparation for wet well lining.
  • Begin painting interior walls