Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
Van Buren Street from 152nd to 144th Avenue will be closed this week to begin preparations for pipe laying. The Contractor recently sent out a letter describing the anticipated work activities.
K&R is approaching Buck Fever Drive with pipeline installation. They should cross the drive first thing this week and continue progressing east from 160th.
Van Buren Street from US-31 to 120th Avenue is closed.
K&R continued laying pipe east of 128th Avenue. Next week, they will continue to lay pipe. Pipe laying is approximately 1,000’ east of 128th Avenue.
New Holland Street from 104th Avenue to 96th Avenue is closed.
Ric-Man completed initial pipe installation in New Holland Street last week. See attached photo of the last piece of existing pipe removed.
This week, Ric-Man will begin making connections from the New Holland Street pipe to the easement piping previously installed. Connections will include installation of precast vaults, valving, and piping.