Work Completed Last Week
  • Water main was installed on Catherine from Irwin to Terrace.
  • Water main was pressure tested, flushed and chlorinated on Catherine between Irwin and Terrace.
  • Sanitary laterals were installed on Catherine working from Terrace towards Arthur.
Anticipated Work This Week
  • Sampling and testing of water main placed on Catherine.
  • Continue sanitary lateral installation.
  • Begin storm sewer installation on Catherine between Terrace and Irwin.