Work on Catherine continued this past week with the installation of storm sewer main and sanitary sewer laterals on Catherine between Irwin and Terrace. The water main that was installed between Irwin and Terrace passed all testing and water services are scheduled to begin this week.
Work Completed Last Week
- Storm sewer main was installed on Catherine from Irwin to Terrace.
- Water main testing passed for main installed between Irwin and Terrace. Water main tie in at Terrace was completed in preparation for water services.
- Sanitary lateral installations were completed between Terrace and Irwin.
Anticipated Work This Week
- Water services between Irwin and Terrace will begin today, 03/30/2026.
- Water main installation will begin between Wood and Ambrosia.
- Sanitary sewer installation will begin between Wood and Ambrosia