Progress Report
- Broadway Avenue was closed to all thru traffic between Glade Street and 5th Streets. Traffic may cross Broadway Avenue at Temple and 6th Streets. All other cross streets are closed to/from Broadway Avenue.
- Storm drainage and sewer covers were lowered
- The roadway pavement was milled off
- Full pavement removal began at the east end at 5th Street
- Materials have been delivered to the site
- Work began on some new water main valves in other portions of the City on Hackley near Reynolds and on Hoyt between Norton and Maplewood
The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.
Upcoming Work Planned for Next Few Weeks:
- Water main installation will begin at 5th Street and work west, starting early next week
- Full-depth pavement removal will continue in the middle and north portion of the roadway from 5th Street to the west and begin at Temple, and work west with a 2nd crew
- Water main installation will begin at Temple Street later next week and work west
Some construction photos of the site on Broadway this week: