Progress Report:

Pavement markings for the Belding Road widening were placed last Monday, and the road was re-opened to through traffic in both directions. Dykema continued working in the public road right-of-way installing the gravel shoulder, grading the drainage ditches/swales, and forming the side slopes at close to finished grades.

Dykema also continued constructing the new road back into the site. With the recent dry weather, the site conditions improved significantly. As shown in the aerial photos, a portion of the road still required filter fabric and extra sand subbase to create a solid foundation. The access road is installed almost back to the community building location. Dykema started cutting down to subgrade for the west parking lot.

Upcoming Work:

Dykema will continue finalizing ditch grades and doing restoration along Belding Road, and they will also continue installing the north end of the access road and the west parking lot.