Work Completed this past week (May 5-9)
- Continued sanitary sewer install on 3rd Street.
- Completed water service install. All houses/businesses transferred over to the new water main.
- Traffic to Red Bud Fitness switch to Skyline Drive. This will remain the route for traffic here until Red Bud is complete.
- Front Street Closed (Eastbound lane only) between Liberty and Rynearson for Retaining Wall repair (not part of Infrastructure project).
Work planned for this week (May 12-16)
- Continue sanitary sewer install on 3rd Street/City Hall.
- Crossing the creek with sanitary sewer on Tuesday.
- Install storm sewer treatment unit once sanitary sewer is across the creek.
- Water main reconnection on 3rd Street in front of Red Bud Fitness planned for Saturday morning (5/17).