Progress Report:

Paving for the Belding Road widening was completed last week. Temporary traffic signals were removed on May 2. PK Contracting will be on site May 4 to place the pavement markings. A shoulder closure on the westbound side will remain in effect until Consumers Energy moves a guy pole/wires and until Dykema finishes constructing and restoring the road shoulder and ditches.

Upcoming Work:

Pavement markings in Belding Road and shoulder and ditch construction along the north side of Belding Road. Dykema also plans to continue road construction northward into the park.