Work Completed this past week (Nov 3-8)
- C1, completed pouring concrete, all concrete North of Front Street complete.
- C1, paved top course, all pavement North of Front Street complete.
- C1, started installing light poles.
- C1, began placing hydroseed East of Red Bud.
- C1, stripping of pavement/parking complete.
- C3, continued pouring concrete on Front Street.
Work planned for this week (Nov 10-15)
- C1, continue restoration.
- C1, continue install on street lights.
- C3, continue pouring concrete on Front Street.
- C3, milling East end of Front Street on Tuesday (11/11) in front of Randy’s building, access to drive will still be open, flaggers will be onsite to manage flow of traffic.
- C3, paving top course on Front Street Thursday (11/13).
- Access to Short Street parking lot will remain on Main Street, see attached map. Flaggers onsite if access routes need to change during paving.