Progress Report:

Last week Black Gold Asphalt completed paving of the remaining sections of the path on Friday. Brenner Excavating finished grading the entire path and began restoration, reseeding portions of the corridor. Brenner also started on the finishing details at Luton Park, including installation of benches, a bike rack, and a bike repair station. Riverworks Construction has nearly completed the boardwalk, with mesh fencing the only remaining item.

Upcoming Work:

Riverworks expects to finish the boardwalk early this week once the fencing is installed. Brenner will continue restoration work along the path and anticipates wrapping up by mid November.