**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. This closure will last as force main construction continues.***
** Heights Ravenna intersection is closed and the closure has been extended to Nov 15th **
Work completed/in progress:
- Completed force main connection north of Crockery Creek.
- Force Main is installed from Wilson St to north of Heights Ravenna Rd.
- HMA base course and top course on Moorland Rd between Heights Ravenna Rd and Mt. Garfield Rd have been paved.
- Moorland Rd is pulverized from Wilson St to Mt. Garfield Rd.
Anticipated work activities for the coming week:
- Continue grading and shaping Moorland Rd south of Mt. Garfield Rd.
- Driveway culvert installation to be continued.
- Start filling force main for hydrostatic testing.
- Perform hydrostatic test on force main.