**Sherman Boulevard is closed from Ensley Road to Price Road.**
**Price Road is closed from Sherman Boulevard to Moorland Road.**
Work completed/in progress:
- Performed hot tap of 60″ force main near MCRRC.
- Force Main installation along Price Rd is completed.
- Concrete restraint collars for force main are completed.
- Driveway culverts and cross culverts along Price Rd have been installed.
- Paved HMA base course on Sherman Blvd.
- Paved HMA base course on Price Rd.
Anticipated work activities for the coming week:
- Continue force main installation near Hall Rd on MCRRC property and on the corner of Price Rd and Heights Ravenna Rd.
- Grade ditches along Price Rd.
- Pave remainder of HMA base course on Price Rd.
- Pave HMA wedging on Sherman Blvd.
- HMA top course on Price Rd and Sherman Blvd is tentatively scheduled for the week of Nov. 10