Work completed/in progress:

  • Pumps delivered to the site!
  • Force main installation
  • Electrical and pump station piping work
  • Medium voltage switch pad extension

Anticipated work activities for the coming week:

  • Pump installation
  • Continued force main installation
  • Continued electrical and pump station piping work