Work Completed

  • Piping from Control Structures A and B to Pond 1 installed
  • Piping from Control Structure A to Pond 2 mostly installed
  • New force main tied in to existing force main and Control Structure A
  • Old pipes in Pond 1 abandoned with flowable fill
  • Began pumping remaining water out of Pond 2

Upcoming Work

  • Excavate for Screening Building foundation and install piping under and around building
  • Coordinate with Biotech Agronomics to remove biosolids from Pond 2
  • Install remaining piping into Pond 2
  • Begin work on Screening Building foundation