Work Completed this past week (Oct 6 to Oct 11)
- C1, completed storm sewer install on Main Street.
- C1, paved city hall an daycare parking lot.
- C1, prepped for paving road on Red Bud, Dewey, and 3rd Street.
- C1, placed sand/gravel on Red Bud North of 3rd Street.
- C3, continued street light install on Front Street.
- C3, CCTV and mandrel of sanitary sewer on Front Street.
Work planned for this week (Oct 13 to Oct 18)
- C1, paving Red Bud (South of 3rd), Dewey, and 3rd Street Monday (10/13).
- C1, pouring curb on Main Street Wednesday.
- C3, beginning sidewalk removals on Front Street Monday.
- C3, pouring curb starting Tuesday.
- C3, continue installing street light foundations/conduit on Front Street.
- C3, continue road building/prepping for sidewalk on Front Street from Days to Oak Street.
- Access to Short Street parking lot will remain on Main Street until further notice. Flaggers onsite if access routes need to change during paving.