Van Buren – Butternut to US-31
- Van Buren from Butternut to US-31 is closed.
- The first layer of asphalt has been paved from 140th through to west of US-31
- The final layer of asphalt has been paved from 152nd to 144th.
- The restoration crew continues to rebuild ditches between 144th and 136th. West of 144th has been seeded.
- There will be some excavation work this week near 140th Avenue to locate and seal up an access point to the transmission main.
164th – New Holland to Van Buren
- 164th Ave is closed between New Holland and Van Buren.
- Transmission main installation continues. Approximately 3,000’ of TM has been installed in 164th Avenue and approximately 2,000′ remains.
- Welding inside the pipe along 164th Ave pipeline will begin this week.
Van Buren – US-31 to 96th Avenue
- Van Buren from US-31 to 112th Ave is closed.
- The Van Buren/120th Avenue intersection was paved and re-opened over the weekend.
- Road building between 128th and 124th is mostly completed.
- Road building between 124th and 120th has begun.
- Transmission main installation has progressed to approximately 900′ east of 120th Avenue and is continuing eastward.
- The tunneling operation beneath US-31 has been suspended for the time being.
New Holland – 104th to 96th & Easement
- Van Buren Street between 104th and 96th Avenue is closed.
- Work continued on pipe appurtenances adjacent to Van Buren Street and Barry Street.
- The transmission main has been filled and acceptance testing is underway.
- Restoration work within the SW of Blendon and Bosch & Hulst Drains is expected to begin this week.