Work Completed this past week (Sept 22 to Sept 26)
- C1, completed sanitary sewer install on Red Bud
- C1, completed storm sewer install on Dewey West of Main.
- C1, finished paving approaches on 3rd East of Red Bud and cul de sac at Daycare.
- C1, began backfilling retaining wall.
- C1, completed concrete placement on 3rd Street East of Red Bud.
- C1, pouring concrete pad over culvert on Red Bud.
- C1, completed installing street light bases on Red Bud and Dewey.
- C3, continued sanitary sewer install on Front Street up to Oak Street.
- C3, began storm sewer install on Main Street.
- C3, road sand/gravel placed on Front Street up to Main Street.
Work planned for this week (Sept 29 to Oct 3)
- C1, continue storm sewer install on Red Bud North of 3rd Street.
- C1, pour curb/gutter on Dewey, Red Bud, and 3rd Street.
- C3, continue storm sewer on Main Street.
- C3, continue sanitary sewer at Front/Oak Street.
- Access to Short Street parking lot will change from Short Street to Main Street starting Tuesday morning (9/30). See attached map.