Work Completed this past week (Sept 1-6)
- C1, continued placing gravel on Dewey St. between Red Bud and Main Street.
- C1, completed sanitary sewer install on 3rd Street between Red Bud and Short Street.
- C1, continued installing storm sewer on 3rd Street between Red Bud and Short Street.
- C3, continued sanitary sewer install on Front St. between Main and Days.
- C3, continued installing electrical conduit and street light bases.
Work planned for this week (Sept 8-12)
- C1, sanitary lateral install on Main Street.
- C1, backfilling behind curb on 3rd Street East of Red Bud.
- C1, prepping for sidewalk on Red Bud.
- C1, begin installing retaining wall on Red Bud.
- C1, continue installing electrical conduit/street light bases on Red Bud/Dewey.
- C1, paving 3rd Street from Skyline Drive to Red Bud Trl. on Thur (9/11) and Friday (9/12).
- C3, begin pouring curb at Front/Red Bud Monday (9/8).
- C3, continue sanitary sewer install on Front Street between Main and Days.
- Access to Short Street parking lot will shift from Main Street to Dewey Street on Monday, see map above.