Work Completed this past week (Aug. 18 to Aug. 23)
- C1, Finished storm sewer install on Dewey.
- C1, began removing old retaining wall on Red Bud.
- C1, began placing curb on 3rd Street.
- C3, completed storm sewer install East of McCoy Creek on Front street.
- C3, completed sand/ gravel placement at Front/Red Bud.
- Access to Phillip 66 gas station switched back to South Red Bud.
Work planned for this week (Aug. 25 to Aug. 30)
- C1, continue road building on Dewey West of Red Bud.
- C1, continue retaining wall install on Red Bud.
- C1, continue sanitary sewer install on 3rd Street West of Red Bud.
- C1, continue pouring curb on 3rd Street.
- C3, begin sanitary sewer install on Main Street.