Progress on the Adrian Pedestrian Tunnel will certainly be picking up steam after Spring Break and the Easter Holiday.
Progress Report
- Drainage system is installed up to the base of the tunnel
- Traffic shift and lane reductions were put in place this week
- The relocated water main pipe has been installed and is in the testing phase before connecting it to the system
- Excavation has begun for the tunnel and walls
- Utility relocation coordination continues – splicing of communication lines in preparation of relocation is ongoing
- Additional construction materials and pipe were delivered to the site
Upcoming Work Planned for Next Few Weeks:
- Water main relocation should be completed next week – Disruptions to drinking water may occur at the end of the week for tie-ins to the existing system. This will affect residents for a few hours during the day on M-52 between Crystal Spring Avenue and Merrick Street.
- Communication cable splicing will continue for the relocation of phone lines on the east side of M-52
- The first section of the precast tunnel could be delivered and installed late next week!
Traffic shift in place:
Photos from the site this week from Mannik & Smith Group: