Progress Report:

K&R continues to lay 21-inch gravity sewer along 120th Ave heading north towards James Street.

Upcoming Work:

The closure of the James Street and 120th Ave intersection is scheduled for MONDAY, SEPTEMBER 21. See the map above for the respective detour routes. Local traffic will have access to their property for the duration of the closure.

Local traffic will have access as follows: