**Enlsey Road north of Sherman Blvd is closed.***
Work completed/in progress:
- Installed approximately 3,100′ of force main north and south of Apple Avenue.
Anticipated work activities for the coming week:
- Install approximately 100′ of HDPE force main north of Apple Avenue and restore easement area.
- Begin force main installation in Ensley Road progressing north to south.