Work completed/in progress:
- 48-inch and 42-inch sanitary sewer and manholes were installed.
- The wet well lid forms were stripped.
- Remaining conduit, floor sleeves, and top mat of steel were installed in the dry well lid.
Anticipated work activities for the coming week:
- The dry well lid is scheduled to be poured Tuesday.
- Installation of sanitary sewer will continue.