Progress Report:

As you may have seen, The Contractor (Brenner Excavating) is preparing to start construction this week. They have staged some of their equipment in the parking lot off of Kies Street. Construction staking is underway and should be completed from Luton Park through Hickory Court by the end of the week. The Contractor will begin removing topsoil shortly.

Upcoming Work:

The Contractor will continue to remove topsoil and clear the route for the path working east from Luton Park.

Most of the trees to be removed have been marked, but all should be marked by August 28 in anticipation of Alpine Tree Service starting tree removals on Monday August 31.