Progress Report:

Kentwood Excavating is making good progress installing water main along Hillsdale Avenue and Lindburg Avenue. A second pipe crew will be on site today to complete the water main installation on Chadwick Avenue this week. Kentwood Excavating continues to work with the Plainfield Water Department to pressure test and disinfect new sections of water main as they are completed.

Upcoming Work:

Kentwood Excavating will complete the first water main connection and begin water service replacements next week. Kentwood has a directional drill contractor lined up to be on site the week of August 10 to replace water service lines under the roads.