Road and sidewalk rebuilding is in full swing on Irwin Ave. and the western limits of Catherine Ave. Water services continued at the eastern limits of Catherine Ave last week. Water services and road rebuilding will continue this week.
Work Completed Last Week
- Began installing curb and sidewalk on Irwin and Catherine between Irwin and Ransom.
- Driveway approaches installed on Irwin Ave.
- Final grading in preparation for asphalt completed on Irwin and Catherine from Irwin to Arthur.
- Paved asphalt base course in Irwin and Catherine up to Arthur.
Anticipated Work This Week
- Continue installing sidewalk on Catherine between Irwin and Terrace.
- Continue installing curb on Catherine from Arthur and Terrace.
- Continue installing driveway approaches on Catherine between Irwin and Terrace.
- Continue installing water services on Catherine between Terrace and Ambrosia St.
- Begin road rebuilding on Catherine between Terrace and Pine St.