This project update provides the public with an update regarding work occurring on site and direction of traffic.
Tyler Street water main will remain under construction this week and traffic should avoid Tyler Street when able. Dykema will only be having a crew starting tomorrow working on 48th Avenue at the Rush Creek Crossing resulting in a full closure to local traffic. Local traffic north of Rush Creek (including condo traffic on Chatsworth Creek Drive and Faringdom Grove Drive) should access their condos now from the north (Baldwin Street) during construction. No work during this time will be occurring north of Tyler Street to facilitate the flow of local traffic in and out of the work area.
We ask local traffic to continue to be mindful of the work occurring and we appreciate everyone’s patience during construction.